← Back to mapScoring RubricMonitoring Playbook

Site Scoring Rubric

Central Ohio Data Center Site-Scoring Rubric

Phase 3 deliverable | July 2026


Methodology

Sites are evaluated using the sequential filter model from national industry practice (Bloom, CBRE, Global Data Center Hub). A jurisdiction must pass each tier before scoring matters at the next. Within tiers, scores of 1–5 are assigned; total scores are only meaningful among jurisdictions that pass all disqualifiers.

Disqualifiers (automatic exclusion)

Tier Disqualifier
Power No AEP/MISO transmission access within 10 miles; no substation headroom; interconnection queue >6 years with no BYOP pathway
Fiber >25 miles from major fiber route with no build plan
Regulation Active moratorium or ban on data centers; statewide ballot measure passed that bans or blocks >25 MW facilities
Water 100-year flood plain with no mitigation; sole-source aquifer with no capacity
Land <50 developable acres for hyperscale; hard seismic/hazard

Scoring Criteria by Tier

Tier 1: Power (weight: gatekeeper)

Score Criteria
5 Confirmed MW allocation in AEP queue; existing 138kV+ corridor; MTEP-26 load-growth project earmarked
4 Load study filed (PUCO docket); substation within 2 miles; transmission line visible on AEP maps
3 AEP service territory; agricultural land near existing transmission; no known queue backlog
2 AEP territory but known congestion (Franklin County core); pending DCT tariff compliance
1 Edge of AEP territory; rural cooperative power only; no transmission infrastructure

Data sources: AEP Ohio Data Center Tariff, PUCO Case 24-508-EL-ATA, MISO MTEP-26 filings, AEP transmission planning documents.

Tier 2: Fiber (weight: high)

Score Criteria
5 Within New Albany International Business Park fiber spine; Ohio IX proximity
4 Within 5 miles of existing hyperscaler campus (fiber follow-on likely)
3 Within 10 miles of Columbus metro fiber ring; along I-71/I-70 corridor
2 Rural exurban; fiber build required but feasible
1 Remote; no existing fiber; significant build cost

Tier 3: Regulation / Social License (weight: high)

Score Criteria
5 Pro-data-center ED policy; permissive industrial zoning; no opposition history
4 Neutral; standard conditional-use process; no moratorium
3 Considering restrictions; community meetings scheduled; ED active but cautious
2 Active opposition; restrictive zoning under review; moratorium under discussion
1 Moratorium or ban in effect → DISQUALIFIED

Tier 4: Water (weight: moderate)

Score Criteria
5 Municipal water with excess capacity; not in CORWS gap zone
4 Municipal supply adequate; CORWS "Easy Does It" scenario
3 Adequate but CORWS "Full Speed Ahead" projects 62 water-supply gaps by 2040
2 Well water only; Pickaway/Commercial Point WTP constraint zone
1 CORWS-identified immediate shortfall; no expansion plan

Reference: Central Ohio Regional Water Study (CORWS), 15-County Report, 2025.

Tier 5: Land (weight: lower)

Score Criteria
5 >500 acres agricultural; single owner; recent option/LOI activity
4 100–500 acres; industrial-zoned or PUD-eligible
3 50–100 acres; rezoning required but precedent exists
2 <50 acres; fragmented ownership; brownfield
1 Hard disqualifier: flood plain, insufficient acreage

Jurisdiction Rankings — Build Probability

Ranked for hyperscale/colocation campuses >25 MW. Scores are composite (average of tier scores where not disqualified). Status as of July 2026.

Tier A — High Probability (active buildout or confirmed pipeline)

Rank Jurisdiction County Composite Rationale
1 New Albany Licking 4.8 Established hyperscale hub; Google/Meta/AWS/Vantage/EdgeConneX/5C; fiber spine; AEP power secured; pro-development ED
2 Johnstown Licking 4.5 AWS operational + planned; Cologix 800 MW AI campus; EdgeConneX Innovation Campus UC; transmission access
3 Hilliard Franklin 4.3 AWS operational 144 MW + 250 MW UC; AEP territory; some community opposition (fuel cells)
4 Jeffersonville Fayette 4.2 AWS $5B campus (inventory 1,155 MW; AES area load cites ~1.5 GW); greenfield; fewer moratoriums
5 Millersport Fairfield 4.0 Vantage 800 MW planned; spillover from Licking County saturation
6 Marysville Union 4.0 AWS $1B AI campus UC (IT MW undisclosed); Union County ED active; Jerome Twp moratorium nearby but permits issued Dec 2025
7 Heath / Hebron Licking 3.8 Microsoft Hebron UC (reactivated Feb 2026); near Johnstown cluster

Tier B — Medium Probability (planned but contested or constrained)

Rank Jurisdiction County Composite Rationale
8 Dublin Franklin 3.5 AWS operational; affluent suburb; increasing scrutiny
9 Pataskala Licking 3.5 Meta Sidecat 117 MW planned; residential adjacency concerns
10 Lockbourne Franklin 3.4 Google expansion planned; near Rickenbacker logistics corridor
11 Lancaster Fairfield 3.3 Google operational; limited expansion room
12 Plain City Madison/Franklin 3.0 AWS CMH086 operational (25 MW); considering restrictive zoning
13 Jersey Township Licking 3.0 Smart Farms/Karis permits filed; rural; less opposition than core
14 Wilmington Clinton 2.8 AWS $4B campus planned (annexation Aug 2025); overflow market
15 Delaware (city) Delaware 2.8 Citi 21 MW planned; suburban; no moratorium but cautious

Tier C — Low Probability (moratorium, denial, or disqualifier)

Rank Jurisdiction County Composite Rationale
16 Sunbury Delaware 1.0 Moratorium through Jan 2027; AWS $2B planned but blocked
17 Grove City Franklin 1.0 Moratorium enacted Jun 1 2026; expires ~Jun 2027; Stream/Headwaters blocked
18 Ashville Pickaway 1.0 Annexation denied Feb 2026; EdgeConneX 680 acres rejected
19 Trenton Butler 2.0 250 MW proposed; W.A.T.E.R. opposition; no moratorium yet but high resistance
20 West Jefferson Madison 1.0 Resolution opposing large-scale DCs (Feb 2026)
21 St. Albans Township Licking 1.0 First Licking County ban (Mar 2026)
22 Washington Township Franklin 1.5 360-day moratorium (after Dec 2025 90-day; still active as of Apr 2026)
23 Jackson Township Franklin 1.5 Moratorium on Amazon fuel cells (Hilliard adjacency)

Tier D — Emerging / Watch List (permissive, under-radar)

Rank Jurisdiction County Composite Rationale
24 Coshocton Coshocton 3.5 Aligned Conesville 117 MW; former power plant site; Frontier Power
25 Bowling Green Wood 3.5 Meta $800M AI campus planned 2027; training-campus profile
26 Lima Allen 3.0 Overflow from Columbus saturation (Signal Ohio)
27 Conesville area Muskingum 3.0 Aligned repurposing coal plant infrastructure
28 Madison County (unincorporated) Madison 3.2 No zoning in many townships; AWS spillover candidate
29 Pickaway (ex-Ashville) Pickaway 2.5 AWS 234-acre site; EdgeConneX may reintroduce Ashville
30 Fayette County (rural) Fayette 3.8 Jeffersonville anchor; additional greenfield likely

Application Workflow

  1. Start with AEP transmission map — identify substations with headroom in MTEP-26 load-growth zones
  2. Cross-reference county auditor — large recent land transactions (>100 acres, LLC buyers)
  3. Check planning portal — rezoning, annexation, conditional use in Tier A/B jurisdictions
  4. Scan PUCO dockets — new load study filings in target counties
  5. Apply disqualifier screen — remove moratorium/ban jurisdictions
  6. Score survivors — rank by composite; prioritize Tier D watch-list for early signals

Statewide Risk Factor

Conserve Ohio / Ohio Residents for Responsible Development ballot initiative would add Article II, Sec. 36a to the Ohio Constitution, flatly prohibiting construction of any "data center" — defined as building(s)/infrastructure on a single or contiguous/aggregated parcel used primarily for digital-info services with aggregate monthly demand or peak load >25 MW, "however derived from any energy source, or combination thereof" (i.e. it would also capture behind-the-meter generation, not just grid draw). The section is self-executing — no enabling legislation needed if it passes, a harder ban than a statute the legislature could later soften. Full text: Ohio AG initiative-petition filing.

Ohio Ballot Board certified the petition Apr 2, 2026. The measure missed the November 2026 ballot — organizers gathered only ~76,626 of the ~413,000 valid signatures required (10% of the last gubernatorial vote) by the Jul 1, 2026 deadline, ~18% of goal (Ohio Capital Journal). Gathered signatures remain valid; organizers are retargeting the 2027 general election and say campaign activity continues unabated. If it later passes, Tier A–D rankings above would be largely superseded for new >25 MW projects — including phased/contiguous-parcel campuses (the New Albany/Johnstown build pattern) that individually stay under 25 MW but aggregate above it.